July 17, 2018 Update
Morris Avenue – concrete works ongoing. Manitoba Avenue Pathway – concrete works ongoing where pathway and approaches meet. Manchester Avenue – asphalt approaches scheduled to begin week of July 23rd…
Morris Avenue – concrete works ongoing. Manitoba Avenue Pathway – concrete works ongoing where pathway and approaches meet. Manchester Avenue – asphalt approaches scheduled to begin week of July 23rd…
Mercy Street – all east and west roads have been tied in with asphalt and completed today (July 13th). Local traffic only. Mercy to be opened completely tomorrow morning. Vaughan…
Mercy Street – asphalt paving is near complete. Remaining intersections to be completed Friday, July 13th. Will be fully opened to vehicular traffic in the morning of Friday, July 13th.…
Manchester Avenue – The paving crew is onsite this afternoon and are scheduled to be finished around noon tomorrow (Wednesday, July 11th). We anticipate that the street can be accessed…
Manchester Avenue asphalt paving is starting this afternoon and should be completed by the end of the day tomorrow, July 10th. Mercy Street asphalt paving is scheduled to start Wednesday,…