August 3, 2018 Update
Vaughan Avenue – Sod work will be completed on Tuesday, August 7th. Morris Avenue – Asphalt work to begin Tuesday, August 7th.
Vaughan Avenue – Sod work will be completed on Tuesday, August 7th. Morris Avenue – Asphalt work to begin Tuesday, August 7th.
Dufferin Avenue – asphalt overlay begins today and will be finished on Monday, July 30th. Vaughan Avenue – approaches and road tie-ins are scheduled for Monday, July 30th.
Vaughan Avenue – Packer was onsite today. Asphalt work to begin tomorrow (July 26th) Manchester Avenue – Asphalt approaches completed. Mercy Avenue – Asphalt approaches completed. Morris Avenue – Work…
Vaughan Avenue – Asphalt work begins Monday, July 23rd. Manchester Avenue – Driveway approaches to be started on Monday, July 23rd. Mercy Avenue – Asphalt approaches scheduled to begin week…
Mercy Avenue – Sod placement and watering continuing. Asphalt approaches scheduled to begin week of July 23rd to 27th. Vaughan Avenue – Gravel grading and packing continues. Manchester Avenue –…