Mercy Street – asphalt paving is near complete. Remaining intersections to be completed Friday, July 13th. Will be fully opened to vehicular traffic in the morning of Friday, July 13th.

Vaughan Avenue – no activity scheduled for today (July 12th) or tomorrow. Gravel works scheduled for Monday, July 16th.

Dufferin Avenue – no activity scheduled for the next 2 weeks.

Reid Avenue – asphalt paving near complete today (July 12th). Remaining asphalt scheduled in approximately 1 weeks time.

Sutherland Avenue – scheduled for work to begin mid to late August.

Manchester Avenue – asphalt road paving complete. Asphalt approaches being worked on today (July 12th) and tomorrow.

Morris Avenue – land drainage rail crossing complete today (July 12th). Curb and gutter work scheduled for Monday, July 16th.

Manitoba Avenue Active Pathway – sodding and seeding ongoing today (July 12th) and tomorrow. Existing concrete tie-in repair work approximately 1 week from today.