Update: September 16, 2022
Eveline Street Reconstruction: Silva cell installation has been completed between Eaton and Dufferin. Curb and gutter concrete is being poured today between Dufferin and Manitoba and will continue as long…
Post Type to identify and post infrastructure projects in the City of Selkirk.
Eveline Street Reconstruction: Silva cell installation has been completed between Eaton and Dufferin. Curb and gutter concrete is being poured today between Dufferin and Manitoba and will continue as long…
Eveline Street Reconstruction: Silva cell installation and boulevard excavation continues between Eaton and Dufferin. Access to the Gordon Howard Senior Centre will be crossing over Eveline at Manitoba Avenue. Access…
Eveline Street Reconstruction: concrete pouring is scheduled for tomorrow (Thursday, September 8) on the round about. *Reminder – effective Friday night, anyone wishing to park at the Selkirk Legion will…
Eveline Street Reconstruction: construction crews will not be working on Monday, September 5th. After the long weekend, concrete framing and pouring will continue on the round about. Effective next Friday…
Please be advised that the entire intersection of Eveline Street at Manitoba Ave. will be excavated on Monday, August 29, 2022, and will cause the following changes to the area:…