Update: August 8, 2022
Eveline Street Reconstruction: gravel base work still being done on the round about on Eveline by Selkirk Park entrance. On the west side of the street between Clandeboye and Eaton,…
Post Type to identify and post infrastructure projects in the City of Selkirk.
Eveline Street Reconstruction: gravel base work still being done on the round about on Eveline by Selkirk Park entrance. On the west side of the street between Clandeboye and Eaton,…
Eveline Street Reconstruction: on the west side of Eveline, gravel base work is ongoing on the round about. Boulevard prep is ongoing between Dufferin and Superior with concrete pouring beginning…
Eveline Street Reconstruction: project continuing on the west side of Eveline Street with gravel base work being done on the round-about. Boulevard prep work is ongoing between Queen and Superior…
WEST SIDE: Queen to Superior – boulevard preparation is ongoing for remaining paving stones. The work is expected to begin within mid August. Superior to Clandeboye – sidewalk prep continues,…
Eveline Street Reconstruction: construction work on the west side of Eveline between Eaton and Queen continues. The contractor is continuing with concrete work, brick work and installing silva cells. Excavation…