July 10, 2018 Update
Manchester Avenue – The paving crew is onsite this afternoon and are scheduled to be finished around noon tomorrow (Wednesday, July 11th). We anticipate that the street can be accessed…
Post Type to identify and post infrastructure projects in the City of Selkirk.
Manchester Avenue – The paving crew is onsite this afternoon and are scheduled to be finished around noon tomorrow (Wednesday, July 11th). We anticipate that the street can be accessed…
Manchester Avenue asphalt paving is starting this afternoon and should be completed by the end of the day tomorrow, July 10th. Mercy Street asphalt paving is scheduled to start Wednesday,…
Manchester Avenue will have curb and gutter framing and pouring starting Monday, June 18, 2018. You will not have access to your driveway for approximately 5 days.
Vaughan: Curb & Gutter excavation has begun, expect minimum to no driveway access during the week of June 4th to 8th. Manchester: Wastewater project complete, road excavation to begin immediately.…
Due to unfavorable soil conditions, we have made a decision to cut a trench in order to access the new wastewater sewer on Manchester Ave. In an effort to save…