Update: August 5, 2022
Eveline Street Reconstruction: on the west side of Eveline, gravel base work is ongoing on the round about. Boulevard prep is ongoing between Dufferin and Superior with concrete pouring beginning…
Eveline Street Reconstruction: on the west side of Eveline, gravel base work is ongoing on the round about. Boulevard prep is ongoing between Dufferin and Superior with concrete pouring beginning…
UPDATE: The Public Hearing was completed; please see Council Meeting Minutes for the decision and outcome.
Eveline Street Reconstruction: project continuing on the west side of Eveline Street with gravel base work being done on the round-about. Boulevard prep work is ongoing between Queen and Superior…
Concerns over gathering and Covid-19 mean that Selkirk residents will be placing their votes in the Oct. 26 election in different locations than in previous years. The Manitoba School Boards…
WEST SIDE: Queen to Superior – boulevard preparation is ongoing for remaining paving stones. The work is expected to begin within mid August. Superior to Clandeboye – sidewalk prep continues,…