Sophia Street Sewer Separation – boulevard restoration continues with an assessment of sod ongoing.

Robinson Avenue Boulevard Extension – concrete and asphalt works complete. Boulevard restoration will begin after current heat wave subsides.

Manitoba Avenue Sidewalk Installation – concrete works complete. Boulevard restoration will begin after current heat wave subsides.

Manitoba Avenue Pathway – hydrant relocations completed. Excavation ongoing with aggregate base product to follow immediately behind all driveways.