Infrastructure Update - Sept 12

Here is this week’s infrastructure update for current projects underway in the City of Selkirk.

🔹Main Street North Landscaping & Naturalization

The project continues to undergo scheduled weed management as part of the naturalized landscape establishment.

Full details on the project including descriptions and benefits to naturalization are available here.

🔹 200 Block of Taylor Avenue & 400 Block of Eveline Street

Land drainage work will begin the week of September 24th and is expected to take approximately two weeks to complete. Paving will follow approximately two weeks later with the entire project anticipated to be completed by the end of October.

Please note that no parking will be permitted on Taylor Avenue between Main Street and Eveline Street until further notice.

About the project:
The City is upgrading underground infrastructure on the 200 block of Taylor Avenue and the 400 block of Eveline Street to make the street safer, more reliable, and more accessible for both motorists and pedestrians. On Taylor, a new sidewalk will be added to the south side, connecting to the city’s existing pathways and supporting active living. The new watermain will extend service life and improve service to the area, which has been prone to watermain breaks in recent years, while wastewater pipe renewal will improve service and reduce the risk of sewer failure.

🔹 Mercy Street Bike Lane & Resurfacing

The bike lane between Manchester Avenue and McLean Avenue is about 70% complete. Crews are continuing with work north of McLean Avenue to Greenwood Avenue. Gravel basework is ongoing in the excavated areas and this should be completed by the end of next week.

If you are walking along the gravel base of the bike lane as it is now, please be mindful of the uneven surface. Asphalt work is anticipated to be completed within the next couple of weeks.

About the project:
The addition of this protected bike lane will allow cyclists to travel north/south safely from one end of Selkirk to another and will connect cyclists to Selkirk’s existing Active Transportation Network. The new road surface will create a safer, more accessible street surface and improve driving conditions while lessening strain on vehicles.

We appreciate your patience as these important improvements are completed. If you have questions about any of the projects listed above, please contact CitizenSupport. Learn about the 2025 infrastructure projects and Selkirk Capital Asset Management Program here: www.myselkirk.ca/city-services/public-works/infrastructure-projects